Help with Instructions? Correct Frost Depth, and Nailing Schedule for OSB

Today the PBG attempts to assist with finding some instructions, the correct frost depth, and nailing schedule for OSB.

DEAR POLE BARN GURU: A friend of mine gave me a cannonball track and hardware setup for my pole barn garage. I have looked everywhere for INSTALLATION INSTRUCTIONS. I cannot find anything on line. Can you please tell me where to look. I would appreciate any help you can give. Thank you. RAY

DEAR RAY: Your request could pose some challenges as Cannonball was acquired by one of their competitors, Western Products of Indiana January 1. We use sliding door systems from a Cannonball competitor, so all of the parts are not exactly the same. I’ve searched online for the installation instructions with the same results you have found – none. Best bet is to try to call Cannonball direct and see if they can assist. (800)766-2825

 

DEAR POLE BARN GURU: Hello , was wondering if you could tell me the depth I need to be at for a pole barn ( garage ) it is going to be 24’x32’. I’m using 4×6” PT poles and going to put them about 10’and 12’ apart on center. I live in Indianapolis on the north side. When I looked up the National frost depth for my area it showed 54”, thought it was a bit deep for here, but want it to be safe as well as lasting. Thank you for any advice you could give. ROBERT in INDIANAPOLIS

DEAR ROBERT: The column depths will be specified on the sealed plans produced by your RDP (Registered Design Professional – architect or engineer). If they are missing you should contact the RDP directly to receive clarification. In no instance should the bottom of the column holes be above the maximum frost depth, which in your case would mean 54 inch deep holes. When it comes to post frame buildings – the last place to scrimp on or cheap out is the foundation. With the correct diameter concrete footings, proper depth and provision for uplift resistance (all of which your RDP should have addressed) you should be off to a terrific start.

DEAR POLE BARN GURU: Your project # 18-0112F. Can someone show where I can find the nailing schedule for the OSB that goes on the roof?? Thanks JIM in KINGSTON

DEAR JIM: The nailing schedules for sheet sidings and sheathing is always found on the “A” pages of the engineered plans provided with your building. Usually they are in a tabular box.

For those who are reading and somehow did not invest in a Hansen Pole Building kit package – if the nailing is not found on your plans, do not guess or take a chance – contact your RDP (Registered Design Professional – architect or engineer) and have them provide a nailing schedule sealed by them.

 

 

 

 