Tag Archives: attic insulation weight

Tin Sheet Ceiling, Glulaminated Columns, and Wood on Grade

This week the Pole Barn Guru answers reader questions about adding tin sheets to the underside of trusses with insulation added, the use of glulaminated columns over rough sawn 6×6’s, and pros and cons of wood on grade vs concrete.

DEAR POLE BARN GURU: I am looking at installing metal sheeting on the ceiling in my pole shed. I would like to screw the tin sheets to the underside of the trusses. I do plan on adding about 18 inches of insulation on top of the metal ceiling. Do I need to install purlins to fasten the tin to for extra support of the tin sheets? Thank you. KEVIN in MANSFIELD

DEAR KEVIN: I know of several builders who would think nothing of screwing steel liner panels to truss bottom chords spaced eight and even nine-foot on center. Personally, I feel like there is going to be some noticeable deflection at those spans, especially as liner panels tend to run towards 29 gauge’s thin side. It is also, obviously, going to depend upon what is being used for insulation. Blown in fiberglass is very light, cellulose or rock wool will be roughly three times as heavy.

In summary, my comfort zone for liner panels is probably in having supports every four to five feet.

 

DEAR POLE BARN GURU: I am looking to build a post frame home utilizing wet set brackets. The cost of laminated 4 ply 2x6s is quite a bit more than solid 6×6 posts. What are the big differences between the two that I should be concerned with? Is one more structurally sound than the other? Thanks! NORMAN in WELLS

DEAR NORMAN: Actually, a typical 3 ply 2×6 true glu-laminated column, will be stronger than a solid sawn 6×6. This is especially true in Western states where solid sawn columns are typically Hem-Fir. Hem-Fir has a lower Fb (fiberstress in bending) than many other popular wood species. Now, some good news for you….Hansen Pole Buildings is expanding to provide metal connector plated trusses, as well as lumber and glu-laminated columns. In buying direct from a well-respected sawmill for lumber and a glu-laminated column manufacturer, we are cutting out scores of middlemen, resulting in us being able to deliver better quality materials, with shorter lead times and at competitive prices. Pricing should be available in roughly 30 days with deliveries to begin around mid-May.

 

DEAR POLE BARN GURU: I studied intently your post about wood on grade floor as an alternative to concrete hydronic slab on grade. Also reading elsewhere about radiant hydronic ceiling using 2′ wide thin panels (Messana.tech) that could install nicely onto ceiling purlins/girts 24″ o.c. on bottom chord of trusses. Do you have any thoughts about that combo to create an affordable 3BR 1250-1500 ft2 pole frame house at rural IA-MN zone 6. New houses within 25mi radius of Roch MN that size sell well at $250K or up. But when median household incomes in small towns like ours are at $50K, that is NOT affordable. Only farmers moving to town can afford a new stick built for $300K or more. BRIAN in LEROY

Gambrel roof pole barnDEAR BRIAN: I find concept of a plywood floor as opposed to slab-on-grade very appealing personally. Many years ago I lived in one side of a rental duplex in Coeur d’Alene, Idaho. I mention it as this duplex had radiant ceiling heat. It was fabulous as long as you were not under something (like your legs when sitting at a table). As heat rises, I would look towards radiant floor heat as my first choice (have it in our barndominium on South Dakota side of Lake Traverse). Fully engineered post frame, modest tastes, totally DIY, move in ready, budget roughly $70-80 per sft of floor space for living areas, $35 for all others. Does not include land, site prep, utilities, permits. If you hire it all done by a General Contractor, expect to pay 2-3x as much.

Things Roof Truss Manufacturers Should Ask

Things Roof Truss Manufacturers SHOULD Ask, But Don’t Always

I didn’t just fall off of a turnip truck yesterday, even though there are a few who may doubt my claim!

Prefabricated metal plate connected wood trusses and I became close friends back in April of 1977. Yes, we had electricity then and no, I did not watch space aliens build Egypt’s pyramids. Eventually I owned and operated two truss plants for 17 years. I know it may sound odd, but I did learn a couple of things.

Most of us do not know to ask (or tell) what we are not asked.  When Hansen Pole Buildings’ Wizardress of Ordering Justine gives information to our trusted truss suppliers, all of these factors below have been incorporated into our order. This insures your trusses will be adequate to handle loads being placed upon them.

Chances are you (as well as most other post frame building kit suppliers and/or contractors) have not taken all of these into account. In failing to do so, your building may not do everything you want it to do not only today, but also years from now (or could even fall down and go boom).

Here we go:

Span from outside of wall to outside of wall. Eave overhangs are not considered as part of a span.

Desired slope(s) – with scissor trusses to achieve a vaulted ceiling or added center headroom, provide an interior or exterior ‘must have’ and other slope will be determined from ‘must have’ slope.

Spacing (ideally you will be using double trusses spaced directly on columns) rather than going into some lengthy dissertation on truss spacing, please read this article: https://www.hansenpolebuildings.com/2011/06/pole-barn-truss-spacing/.

Overhangs on eave sides (measured parallel to ground), as well as beyond endwalls. Why is beyond endwalls important? For sake of discussion assume single trusses placed every two feet, unless specified and designed otherwise and end truss in this scenario can only support a foot of overhang past an end. Single trusses placed every four feet can support a maximum two foot end overhang.

 

Roofing material and any solar or rooftop arrays. How many psf (pounds per square foot) must your trusses support? Steel roofing is fairly light weight. If using shingles, Code requires incorporation of enough load capacity for a reroofing down the road.

Is roofing over purlins, sheathing? Maybe sheathing AND purlins. Whichever is your case, these weights need to be accounted for as top chord dead loads.

Ceiling? If not now, ever? One of my most asked questions is in regards to adding ceilings in existing post frame buildings. At a bare minimum to support steel liner panels bottom chord dead load should be three psf, for gypsum wallboard (sheetrock) five psf. Last year Hansen Pole Buildings opted to increase bottom chord dead load for all trusses spanning 40 feet or less to five psf. We do not frankly do a very good job of promoting the benefits of this feature.

If attic is insulated, weight of ceiling material, ceiling joists and attic floor insulation.  

Design wind speed and exposure. More buildings fail from roofs blowing off, than from snow. Depending upon Code year and version, wind speed may be expressed as Vult or Vasd. There is a difference and whoever is going to build trusses needs to know. If you do not fully understand differences between B and C wind exposure, learn quick: https://www.hansenpolebuildings.com/2012/03/wind-exposure-confusion/

Heated or Unheated? There is a factor relating to whether your building will be heated and it influences design snow load. Heated buildings help melt snow off.

Overall building dimensions: width, length, height above grade. These factors impact wind design.

Risk Category – How your building will be used impacts design snow and wind loads. Buildings with infrequent human occupancy have less risk and can be designed for a greater probability of failure in event of an extreme weather event.

Energy heels for full depth attic insulation? If ever insulation might be blown into a dead attic space for purposes of climate control, to be effective it should be full depth from outside of wall to outside of wall. For extended reading: https://www.hansenpolebuildings.com/2012/07/raised-heel-trusses/

Siding material (so proper gable truss recommendations can be made). If supporting other than roll formed steel siding, end truss probably will require vertical studs. Without a continuous wall beneath an end truss, it must be ordered as a structural gable.

Is the building fully enclosed, partially enclosed or open? This will again influence wind design.

Are you interested in parallel chords with a heel height to create a vaulted ceiling? You can get the same slope inside and out with this method.

Done right you would be offered options to increase load carrying capacities against either wind, snow or both. This is true value added design. Builders most always want bare minimums, while people who are doing DIY homes or barndominiums are most likely to increase capacities. If in doubt – own the last building standing!

When I was building trusses I  had extremely high expectations of my truss staff, we always wanted to offer designs to exceed our client’s expectations.

Too many factors to juggle? You do not have to fret with an engineered Hansen Pole Building. Please call 1(866)200-9657 today.