Site Slope, Gable End Exhaust Fans, and Setting Trusses

Today’s Ask the Guru blog answers reader questions about building on a slope, a recommendation for gable end exhaust fans, and setting trusses into columns.

DEAR POLE BARN GURU: I always see pole barns being built on level ground. is there any reason my concrete slab, perimeter board, and exterior grade can’t slope 1/4″ per foot from the back to the front of my pole barn garage? I realize the bottom of my metal siding would probably have to be cut at an angle to match the slope. DAVID in WESTFIELD

DEAR DAVID: Could and should are two different animals.

Everything is going to be far easier working from a level site, where grade can be sloped away from building at 5% or greater (a 5% slope is six inches in 10 feet). You don’t want to have water from any direction running towards your building.

International Residential Code (2021 IRC) Section R309.1 and International Building Code (2021 IBC) Section 406.2.4 address concrete floor slope: “The area of floor used for parking automobiles or other vehicles shall be sloped to facilitate the movement of liquids to a drain or toward the main vehicle entry doorway.” Floor slope by IBC only applies to “U” occupancy buildings of 1000 square feet or less. Actual slope requirement is unspecified however a generally accepted minimum is 1/8” per foot. Grade inside of building should be gradually built up to create this slope.

As far as cutting bottom edge of your steel siding to follow a slope, cutting each panel to precisely follow slope would be a difficult, if not impossible task. This also would leave a raw field cut edge in close proximity to ground and it will rust.

 

DEAR POLE BARN GURU: I have a 30×48 pole barn. 13′ at eaves/overhang and 19′ center height because of scissor truss. No windows. One man door and one garage door. It has closed cell insulation. Brown roof. Used for trailer/camper storage. Not a lot of work going on in this building. It stays a little cooler than the outside temperature but is humid with musty smell due to no ventilation. I would like to install a gable end louvered exhaust fan but everywhere i search i come up with different answers. I don’t need fast air movement, just replacement. i would like to know what size fan and air intakes are required to do this. Some of this information may be irrelevant but it was asked for among other inquiries. Thanks for your time and help. WILL in WINFIELD

DEAR WILL: You should plan upon three to six air exchanges per hour. With 23,040 cubic feet of interior space, you need 1152 to 2304 cubic feet per minute (cfm) as an exhaust. A professional HVAC provider can confirm amount of air intakes required, as well as set you up with an appropriately sized exhaust fan.

 

DEAR POLE BARN GURU: I have a question on installing trusses on a 16×40 pole barn. The bottom of all poles are square and measure what they should on the print. Knowing that the 6×6 poles are probably not straight, is there a trick to making sure that I install the trusses straight and square at the top? Always want to double check before Ii start lifting these 14 feet in the air. Thank you for any help. BOB in MOORCRAFT

DEAR BOB: This is one reason I like to build with my trusses directly attached to columns (using notches cut into columns to provide full bearing). After verifying trusses are exactly 16′ in length, trusses can be placed into notches, with outside of truss flush to outside of columns. This solves any width issues. Using recessed purlins, joist hung between trusses, purlins can be pre-cut to length of space between trusses, solving length issues. Once framing is completed, each roof plane can then be squared (read how here: https://www.hansenpolebuildings.com/2020/05/how-to-square-a-post-frame-building-roof/).

Dear Guru: Should I Add Closures?

New!  The Pole Barn Guru’s mailbox is overflowing with questions.  Due to high demand, he is answering questions on Saturdays as well as Mondays.

Welcome to Ask the Pole Barn Guru – where you can ask questions about building topics, with answers posted on Mondays.  With many questions to answer, please be patient to watch for yours to come up on a future Monday or Saturday segment.  If you want a quick answer, please be sure to answer with a “reply-able” email address.

Email all questions to: PoleBarnGuru@HansenPoleBuildings.com

 DEAR POLE BARN GURU:I have a pole building reroofed with 1′ overhangs and am wondering if you think I should/need to use closures or something at the eave to seal the ribs. Thanks FREAKING IN FOSTORIA

DEAR FREAKING: I’d recommend the use of form fitted inside closures on top of the eave girt, if you have enclosed overhangs, or on top of the eave girt with open soffits. There should also be form fitted outside closures on top of the roof steel underneath the ridge cap. This combination will help to keep those nasty little flying critters from joining you inside of your building.

DEAR POLE BARN GURU:water drainage. BUDDY IN HOLLEY 

DEAR BUDDY: Not entirely sure how to best assist you from the two word question. Assuming your new pole building is not going to be used as a home (in which case I would make entirely different recommendations using a raised wood floor), I’d approach this as for any pole building drainage solution. I would order columns long enough to get the required depth to extend below the frost line, plus make up for any grade change. After the columns were set, I’d bring in good compactable fill to get the elevation of the bottom of any future concrete slab above the highest point of the surrounding grade. Above the high side of the building, a French drain can be installed to divert any natural drainage. For those who are unfamiliar with French drains, it is when a trench is dug beyond the building perimeter, drain rock is placed in the bottom, then one or more rows of perforated four inch pipe are laid. After placing the pipe, the balance of the trench is filled with drain rock. I hope this helps – if not…please email me more information.