Order of Construction

Order of Construction

Reader DANIEL in SAINT JOSEPH writes:

“Hi Mike, I am looking to start building in the next year or two on my up north Minnesota cabin land. I was planning on doing my own general contracting to save. In what order would you recommend I schedule the subs to do their work and when should I begin finding the subs? I already have the septic and well installed for my camper.”

Click here to download our free brochure!Mike the Pole Barn Guru writes:

Here is a general construction sequence. In most instances, you want to line up your subcontractors 6-12 weeks prior to needing them. Further ahead, seems to make it difficult to get return calls. A great source of more reliable subs, is by contacting your nearest Home Builders Association and asking for referrals.

1. STAKE LOT
First step of home building is locating your new home on its lot. This will usually involve a surveyor who will come out and accurately drive stakes to locate your home on lot. They will be used by excavators and foundation subcontractors to guide their work.

2. OBTAIN PLANING, ZONING AND BUILDING PERMITS (Where required)

3. TEMPORARY UTILITIES
You will need to have water, electric power, and toilet facilities available during construction process.

4. CLEAR AND ROUGH GRADE
Clearing is removal of trees and undergrowth from actual construction site and yard areas. Rough grading is moving dirt around to establish approximate drainage patterns, yard areas, drive and walk levels, etc. you hope to achieve. Properly compact any fill in no greater than six inch lifts.

5. WELL
If you are going to have a well, you might as well dig it up front so you will have water available for construction.

6. LAY OUT BUILDING

7. DIG HOLES FOR COLUMNS OR PIERS
Call for hole inspection (where required)

8. SET COLUMNS IN HOLES OR INTO WET-SET BRACKSET Backfill per plan

9. INSTALL
a)SPLASH PLANKS
b)TRUSSES AND/OR RAFTERS
c) Purlins and all other roof framing (including ceiling joists and bracing)
d)  roof steel and ridge cap (or sheathing, felt and roofing)
e) any raised wood floor framing and floor sheathing
f) Girts and all other wall framing

10. CALL FOR FRAMING INSPECTION (where required)

11. INSTALL
a)  Weather Resistant Barrier over wall framing
b) Entry doors, sliding doors and windows
c) All steel wall trims except corners
d)  Wall steel and corner trim

 12. SEWER AND WATER TAPS

If you are connecting to municipal water and sewer, this is where pipes are laid to house and actually connected (tapped into) water and sewer mains.

13. UNDER SLAB UTILITIES
Any plumbing and electrical needs to go under concrete slab is installed here.

14. UNDER SLAB VAPOR BARRIER, UNDER SLAB AND PERIMETER SLAB INSULATION, PEX FOR RADIANT FLOOR HEAT

15. SLAB  FLOOR

16. ANY STAIRS RESTING ON SLAB FLOOR
Get these in now so that the subs working inside can get from one floor to the other without depending on ladders.

17. GARAGE DOOR AND EXTERIOR LOCKS
Some people wait until end to get garage door in. But we think having it in place creates a good place to store materials and equipment during construction. Installing exterior locks means whole house is secure.

18. BACK-OUT FRAMING

This is a general category including interior room partition, soffits for wall cabinets, and drywall nailers.

19. FIREPLACE AND CHIMNEY
A prefabricated fireplace should be installed before roughs (below). A prefab will have a framed chimney. A masonry fireplace and chimney can be installed before any brick veneer.

20. ROUGH HVAC
HVAC (heating, ventilation, air conditioning) sub is first of three “mechanical” subs (plumbing, electrical, HVAC) to come to job. He will install duct work for your HVAC system and possibly furnace. He comes first because stuff he puts into walls is biggest and most inflexible.

21. ROUGH PLUMBING

Next comes plumber to install his pipes.

22. ROUGH ELECTRICAL

Codes call for house to be “dried in” before wiring is installed. With exterior windows and doors in place and roof on, it’s time. For roughs, electrician will put in boxes (switch, outlet, and lighting) and will pull wires into them. Cable, telephone, speaker wires, etc. are also installed at this point.

23. ELECTRIC & GAS METER SET
You’ll need these in place to get some heat in house for drywall installation.

24. GUTTERS AND DOWNSPOUTS
It’s good to get water away from house as soon as possible.

25. WALL INSULATION

Once everything else is in walls and rough inspections are completed, it’s time to insulate your home.

26. TEMPORARY HEAT
With meters set (above), HVAC sub can get some temporary heat going. This will be critical for getting drywall joint compound (mud) to dry in a timely fashion. Carpet sub also needs a warm home so  carpet is installed at a temperature comparable to normal living conditions.

27. DRYWALL
Sometimes called “Sheetrock®.” This will be “hung” (screwed to wall girts, studs and ceiling joists), taped (at joints), and “mudded” (joint compound applied) . . . after the in-wall plumbing, HVAC, electrical, and insulation have been inspected!

28. ATTIC INSULATION

29. CABINETS
Base and wall.

30. INTERIOR DOORS AND TRIM

Trim materials installed here may include door casing, base mould, window stool and apron, window casing, chair rail, crown mould, built-in cabinets, stair railing parts, and others. This step also includes hanging doors.

31. PAINT AND WALLPAPER
First coat of paint is usually sprayed. Get it in before hard wood floors are installed.

32. HARDWOOD FLOORS
Now it’s time to install your hardwood floors.

33. COUNTER TOPS
Counter tops are next. this may involve a different sub than one who installed cabinets.

34. VINYL AND CERAMIC TILE
Vinyl floor coverings and ceramic tile are installed. Two different subs.

35. SAND ANF FINISH WOOD FLOORS

This is first of two finishes. The last is done just before you move in.

36. APPLIANCES AND SPECIAL EQUIPMENT

This would include all of your major appliances – washer, dryer, range, oven, refrigerator, as well as any other special equipment you have specified.

37. FINISH ELECTRICAL
Here is where electrician comes back to install switches, outlets, light fixtures, ceiling fans, door bells, etc. He will also hook up appliances, furnace, air conditioner, doorbell, and so forth.

38. FINISH PLUMBING
Plumber will install sinks, lavatories, toilets, and all faucets.

39. FINISH HVAC & FINAL HEAT
Your heating sub will install registers and get furnace and air conditioning running properly.

40. SHOWER DOORS AND MIRRORS
Install shower doors. Hang mirrors.

41. CARPET
Now it’s starting to feel like home!

42. HARDWARE AND SCREENS
Typically, this is door, window, and closet hardware. Window screens.

43. DRYWALL REPAIRS
You may need to get drywall subcontractor back out to patch some dings caused by other subs’ work. This is normal.

44. CLEAN UP
This is final interior clean up.

45. FINAL PAINT
Touching up drywall repairs and so forth.

46. FINAL WOOD FLOOR FINISH
This should be your last inside job before moving in.

47. RETAINING WALLS
These outside home building jobs can be going on while work proceeds inside.

48. WALKS, DRIVES, AND PATIOS
You should wait until drywall has been delivered, because drywall trucks are VERY heavy, and could damage your flat work

49. SEPTIC TANK AND DRAIN FIELD

Same as above on timing with regard to drywall delivery. Septic tank holds waste and allows microbic action on solids. Drain field is where effluent leaches into soil.

50. FINISH GRADING AND LANDSCAPING
Final finished grades are established to ensure proper drainage away from home, and to prepare yard for landscaping. Trees, shrubs, grass, etc. are installed.

 

 

 

 

 

 

 

Pool Inside Pole Barn

Pool Inside Pole Barn

Reader DOUG in SNOHOMISH writes:

“I am just starting the process of having an inground swimming pool installed but due to weather and TREES in my area I have decided to build a Pole Barn to enclose the entire pool.  I have done a lot of research on Pools and Pole Barns over the past 2+ years before coming to this conclusion.  With advice from you and a ex-framer brother I feel that this is the right direction based on cost and complexity level.

What I am missing is real details and examples of individuals that have done similar projects.  I could ask a million questions and spend days just chatting to you and/or other experts  but it is unlikely I would be allowed.    I have been searching the web for examples with more details on the different phases of the construction such as (1) Insulation, (2) Framing Walls, (3) Drywall, (4) Ceiling, (5) HVAC D, (6) Electricial, (7) ETC… but have not found much.  Is there any good information on such projects being undertaken by experienced DIY individuals?  (I know what you are thinking DIY = Don’t Indulge Yourself, but in this case I really am an Experienced DIY, having BUILT my own 4700sf home including either GC or hands on.  

I am really considering using a Hansen Pole Barn Kit for the shell, but need to figure out how to ensure 60% humidity inside the building doesn’t rot it from the inside out.  I know that HVAC Dehumidification will be very import, but so is how to seal the build walls from both the outside and inside, how to insulate the walls and ceiling (especially since we plan to have a flat ceiling thus an attic area where the Ceiling and Roof may need to both be insulated to avoid condensation, etc.

Any advice and especially great examples with details would be appreciated.”

Mike the Pole Barn Guru says:

It has been several years since we provided one of our buildings over a pool. Here is an article I wrote as a result of it and a more recent inquiry: https://www.hansenpolebuildings.com/2019/08/post-frame-indoor-swimming-pool-considerations/

Obviously your key to success is having a great HVAC/R system.

I do try to always err on caution’s side.

Adding to my referenced article above – I would add using all rock wool insulation as it is unaffected by moisture. Have a Weather Resistant Barrier between framing and wall steel (allows water vapor to exit the wall). Consider finishing the interior with cement board over a well-sealed vapor barrier, rather than “green board” moisture resistant drywall. Cement board is comparable in weight to drywall, so will not require adding to structural capacity beyond what sheetrock would take. Have a well ventilated attic (eave and ridge).

You will want to seal the interior – walls and ceiling, while having the exterior able to allow any moisture to escape.

Electrical is outside of my wheelhouse, otherwise you should be “good to go”.

Where Your Barndominium Dollars Go

Where Your Barndominium Dollars Go

Recently published by NAHB (National Association of Home Builders) was their 2019 Cost of Construction Survey. I will work from their ‘average numbers’ to breakdown costs so you can get a feel for where your barndominium, shouse or post frame home dollars go.

Please use this as a reference only, as chances are your barndominium, shouse or post frame home will be anything but average!

2019’s average home had 2594 square feet of finished space and a sales price of $485,128. Without lot costs, general contractor’s overhead and profit actual construction costs were $296,652 ($114 per square foot).

Construction Cost Breakdowns as Follows:

Site Work

Building Permit Fees                                                                                  $5,086

Impact Fees                                                                                                   3,865
Water & Sewer Fees                                                                                     4,319

Architecture, Engineering                                                                           4,335

Other                                                                                                                 719

                       Foundation

Excavation, Foundation, Concrete, Retaining walls and Backfill        $33,511

Other                                                                                                                1,338

                     Framing

Framing (including roof)                                                                            $40,612

Trusses (if not included above)                                                                     6,276

Sheathing (if not included above)                                                                 3,216

General Metal, Steel                                                                                           954

Other                                                                                                                     530

                       Exterior Finishes   

Exterior Wall Finish                                                                                   $19,319

Roofing                                                                                                          9,954

Windows and Doors (including garage door)                                       11,747

Other                                                                                                                671

                       Major Systems Rough-Ins       

Plumbing (except fixtures)                                                                        $14,745

Electrical (except fixtures)                                                                           13,798

HVAC                                                                                                               14,111    

Other                                                                                                                 1,013

                       Interior Finishes       

Insulation                                                                                                  $ 5,184

Drywall                                                                                                        10,634

Interior Trims, Doors and Mirrors                                                           10,605

Painting                                                                                                         8,254

Lighting                                                                                                         3,437

Cabinets, Countertops                                                                             13,540

Appliances                                                                                                    4,710

Plumbing Fixtures                                                                                       4,108

Fireplace                                                                                                       1,867

Other                                                                                                                923

                                              Final Steps

Landscaping                                                                                              $6,506

Outdoor Structures (deck, patio, porches)                                           3,547

Driveway                                                                                                     6,674

Clean Up                                                                                                     2,988

Other                                                                                                              402

Other                                                                                                      $11,156

Considering using post frame construction, rather than stick built and foundation costs will decrease by roughly $10,000 (https://www.hansenpolebuildings.com/2011/10/buildings-why-not-stick-frame-construction/).

Architecture, Engineering, Framing and Exterior Finishes for this average home run an astonishing (to me) $97,614. If labor runs 60% of material costs, this would put a material package at $58,300! At over $20 per square foot, this would be one very, very nice post frame barndominium!

Looking to stretch your barndominium dollars? Considering Doing-It-Yourself, you absolutely can do it!

Planning for a South Carolina Post Frame Home

Planning for a South Carolina Post Frame Home

A barndominium, shouse (shop/house) and post frame home wave is sweeping across America. There are numerous articles available on Hansen Pole Buildings’ website – just click on SEARCH (upper right of any page) and type in BARNDOMINIUM and hit ENTER and relevant articles will appear for your reading pleasure.

Loyal reader LANE in NORTH AUGUSTA writes:

“Hello,

I’m currently planning a post frame home in North Augusta, South Carolina.

I’m planning to build 72x40x16 with a wrap around overhang around one end and part of the front or 84x40x16 with the last 12′ bay open to create the end porch then a lean-to on part of the front. 

I’m curious firstly on the shipping. There are a few local businesses here that sell kits and will erect the building as well if desired. How much will freight affect my final cost if I buy from you vs. sourcing it locally? I haven’t gotten any prices from the local companies yet. I decided to reach out to you guys first because I’ve been reading your blog and it seems like you really have this pole building thing figured out. I’m also really interested in the design and plans that you provide. Do these also include the interior walls, plumbing and electrical, or is it just the shell of the building?

I’ve already drawn up a simple floor plan for the living space that really fits our needs so I’d like to incorporate that.

Thank you for your time. Look forward to hearing back.”

Mike the Pole Barn Guru answers:
Thank you for your interest in a new Hansen Pole Building. We have wholesale relationships all across America and will ship bulkiest items, in most cases lumber and trusses, from your locale – freight costs will be no more for you, than they would be to any other location.

We would like to believe we have at least a reasonable idea of what pole (post frame) buildings are all about :-). It is all we do, unlike your local businesses who also do other things – we are specialists.

With your investment into any complete post frame building kit are detailed structural plans showing every member and all connections. For those with living areas, we have available an offer for interior floor plans: http://www.hansenpolebuildings.com/post-frame-floor-plans/?fbclid=IwAR2ta5IFSxrltv5eAyBVmg-JUsoPfy9hbWtP86svOTPfG1q5pGmfhA7yd5Q. For a nominal fee plumbing and electrical can be provided (a hint – your plumber and electrician will normally provide these at no charge as part of their service).

One of our Building Designers will be reaching out to you shortly to further discuss your ideal new building!