My 22 Year Old Morton Building Roof Leaks

My 22 Year-Old Morton Building Roof Leaks

Reader TERRY in EVANSVILLE writes:

“Dear Pole Barn Guru, we have a 1989 Morton building. The roof was replaced in 2000 due to flaking and peeling paint. Since then, the headers over our large north and south doors have deteriorated, and the barn is leaking on the entire stretch of north and south walls further deteriorating the wood at the top and consequently the bottom as it runs down. I believe this has been happening since the roof was replaced …taking this long for us to notice the damage. I was told that there is a condensation problem. But, water runs from the ridge to the eave. We can see stains on the trusses. There are two places where water has dripped in the middle of the barn. I went up on the roof and inspected the ridge. Appears as though the ribbed metal has been over tightened about every 2 to 3 ft. in a 140 ft. span. In light rains we do not see water running down the walls, in heavy blowing storms, the water runs enough that I have videotaped it. Any words of wisdom or insight to what you think is going on would be greatly appreciated. I’ve been dealing with Morton since March of 2020 with not much success. Also, just a side note… one of their people stopped by in 2016 to look things over…at that time he said he could not adjust the doors. But…gave a $10000 estimate to rebuild, instead of looking into why there was a problem. I think if we had done the repair we would be facing a similar problem today, as the problem seems to have grown worse. Thank you in advance!”

Mike the Pole Barn Guru says:

You could have a plethora of different issues going on.

Start by process of elimination –

Is there a form fitted closure strip under each side of your ridge cap? If you have light coming through the ridge during daylight, then no. Easiest fix, if none, would be Emseal https://www.hansenpolebuildings.com/2016/03/emseal-self-expanding-sealant-tape-closures/

2) Check for leaks. Get a garden hose up on your roof – start by running water at eave lines and have someone inside yell when a leak is found. You only have to do this test on a small portion along your eave line. Pick a spot where interior water stains are greatest. Gradually work your way towards the ridge line. Leaks can usually be fixed by replacing the original screw by one of longer length and larger diameter.

3) Once the above two have been either ruled out or repaired, your problem is condensation. Stains on trusses and purlins are typically a giveaway to this being an issue, especially if they seem relatively consistent from eave to ridge and along length of building. Short of replacing roof steel with a product with an Integral Condensation Control factory applied (read more here: https://www.hansenpolebuildings.com/2020/09/integral-condensation-control-2/), your solution is not inexpensive – have two inches of closed cell spray foam applied directly to underside of your roof steel.

UC-4B Treated Columns, A Connecting Structure, and Custom Options

This Monday the Pole Barn Guru answers reader questions about UC-4B treated columns, advice to connect a new structure to existing building, and if one can customize a monitor style building to eliminate pony wall.

DEAR POLE BARN GURU: We are considering residential post frame construction in southeast Ohio. I’m concerned about wood posts in the ground and trying to avoid permacolumns. I asked the post frame contractor I’m talking to about UC4 treated posts in the ground, specifically UC4B. His response was that building codes changed in the last couple years and all UC4 posts are now treated at the same level, there is no more UC4A/B/C distinction. In your expert opinion, is that information correct? Should I continue discussions with this contractor or walk away? RORY in CHILLICOTHE

DEAR RORY: Your proposed building contractor is talking out of his……..(not mouth) as he obviously has no clue as to what he is talking about. Building Codes dictate UC-4B pressure treating levels for lumber to be embedded in ground structurally. You can look this up yourself at: https://codes.iccsafe.org/content/IBC2021P1/chapter-18-soils-and-foundations#IBC2021P1_Ch18_Sec1807   Go to subsection 1807.3.1

American Wood Protection Association has a detailed listing relating use categories to placement – please  to upper left on Page 3 of this document for definition and where to use UC-4B treated wood. https://awpa.com/images/standards/U1excerpt.pdf


In my humble opinion, it may behoove you to deal with a supplier who can provide you with a fully engineered post frame home to meet Building Code requirements and either erect shell yourself or hire an erector to assemble it for you.

 

DEAR POLE BARN GURU: The picture is of my existing 30x40x10 Pole Barn.  One the back side I’m planning to build an attached a 26X40X16 barn.  The peaks of the barns will in the same direction and aligned in the center.  There is no rear overhang on the existing barn, just a piece of trim like you can seen in the picture on the front side.

My question:  how do I make the connection between the roof on the existing barn and the new wall where they attach?  I can see from some of the pictures on your website that this is somewhat common, but couldn’t find any details.  

The roof on the existing barn is shingles (not steel), will that pose any problems?

If you need more pictures or any other info let me know and I’ll get it for you.

Thank you very much. JON in WAYNE

 

DEAR JON: Assuming new endwall columns for your addition can be placed directly against your existing endwall – framing will extend 1-1/2″ past these columns (effectively creating an overlap above your existing building). A piece of flashing known as sidewall, will go up your new endwall and lap onto your existing roof. Being as your existing roof has shingles, I would order Emseal expanding closures to use on underside of this flashing to seal against water infiltration. Sticky side of Emseal can be placed on flashing (inside of drip leg) and it will expand after installation to fill any irregularities. Wall steel is then applied to overlap this flashing.

 

DEAR POLE BARN GURU: Is it reasonable to design a monitor style pole barn home: 1.5 stories With the central roof lines connecting into the shed roof sides, without the traditional short wall seen on most exteriors? Will I run into trouble creating head space in the central alley of the second floor? I have looked at attic trusses and mono trusses…I had thought to get an 18′ wide, alley with pony/short walls of 4′ – 5′. But it looks like the cut off is 16′ wide with a squared off 8′ tall ceiling. I suppose I could do with the more traditional look, but I want to keep a low profile, and would rather have the ceiling follow the roof line on the interior and not have it be squared off. Is this possible with a pre-built truss system?

Thank you, I love your blog. AMY in STANWOOD

About Hansen BuildingsDEAR AMY: Thank you for your kind words. Depending upon width of side sheds, we could probably have your building engineered using rafters at attached to shed eave side columns, main columns and cantilevered over center portion. Same concept could also be done using parallel chord trusses, however they would take up more depth. In either case, you could have a vaulted ceiling to follow roof lines.

 

 

Closing Top of Corner Trims Revisited

Recently I had posted an article on closing tops of corner trims (https://www.hansenpolebuildings.com/2018/10/closing-top-of-corner-trims/).

Reader MATT in CINCINNATI has opted to go with a light gauge steel framed building, rather than a post frame building, however he had questioned my original article:

“Thanks for all of your informative posts, they have been quite useful in my journey toward my dream barn/house. I am finalizing design of a beautiful K Building. Hard to argue with a full perimeter footer and steel truss frames. My barn will have a porch similar to the attached picture. I am hoping you might revisit your post on “Closing Top of Corner Trims”. I agree in regards to the picture in your original post that spray foam would work when tucked up under the soffit with minimal weather exposure. However, in the attached image, with the top edge of the lower corner trim exposed directly to the weather, it seems much more important to get it sealed. Perhaps slitting into the endwall siding and extending the J trim from the porch past the corner trim would provide a better solution? Either way it seems copious amounts of caulk are in order.”

In an ideal world you could use a combination of #2 (the Emseal expanding closure) and #3 folding down the top of the corner trim. The Emseal by itself will provide a watertight seal. I always try to avoid cutting into the siding as much as possible.

I do have a concern about your K Building’s 2×6 #1 Southern Yellow Pine (SYP) roof purlins, spanning 15 feet.

20 psf * 24″ on center * 15′ span ^2 / 8 * 7.5625 (section modulus of a 2×6) * 1.15 (Cr for repetitive members) * 1.15 (Duration of Load) * 1350 (Fb for 2×6 #1 SYP) = 1

20 psf is the minimum design live/snow roof load by Code, however there is no allowance for dead loads (weight of roofing, weight of the purlin itself, etc.). I would recommend using 2×8 purlins.

Shipped International, Post Protection, and EmSeal!

DEAR POLE BARN GURU: Can the kit be shipped international, like Philippines? ERIC in SUSANVILLE

DEAR ERIC: Post frame building kit packages can be shipped anywhere on the planet. In most cases, the components are delivered to the docks – in your case most likely the Port of Tacoma or Seattle, where it is reloaded into a container. As containers have a maximum exterior length of 40 feet, it will limit the length of any prefabricated wood roof trusses, unless they are designed to be built in halves and field connected.

Many countries will require the lumber to be treated with a fungicide in order to prevent possible contamination of their own forest resources.

 

The furthest I have personally shipped to has been Saipan.

 

DEAR POLE BARN GURU: I really like the idea of post frame construction for residential, not because it is cheaper but because I believe it is stronger. Maybe I should qualify that by saying it is stronger laterally (horizontally) but probably not vertically. What I envision as post frame is having posts made of pressure treated lumber like 6×6, 8×8 etc set deep in the ground in concrete, and these posts would extend to the top of the wall or where the roof begins.

My question is do you know of methods of treating the wood so that it does not rot so quickly? I was thinking that if one were to coat the wood in epoxy resin that would help greatly, but I don’t know. Or could you not encase it in some kind of liquid plastic that once dried you would stick the post in the ground. Thanks. JACK in COBB

DEAR JACK: Post frame buildings are actually incredibly strong in the vertical (compressive) direction as properly braced timbers can withstand a very large downward force. Post frame buildings will be more economical than any other permanent building system, as well as affording greater flexibility for architectural design.

Properly pressure preservative treated lumber will outlive you, me and probably our grandchildren. If I did not believe so, I would not have invested the money in owning three of them myself, including the 8000 square foot finished building we live in. If you are yet concerned about longevity, there are currently available commercial products which will isolate the columns from the surrounding encasement (https://www.hansenpolebuildings.com/2012/04/plasti-sleeves/).

 

DEAR POLE BARN GURU: Hi Mike, I recently found this blog and man is it helpful. I have been remodeling a 1977 24×40 pole building. Never had one before and I’m learning as I go… hoping I can build a new one later in my life I’m only 29. I completely replaced the roof/trusses etc. and installed bubble insulation under steel for condensation. No soffit only Ridge vent. I want to seal up my gables up to peak. How should I do this? Solid closure strips? Vented closure strips? Or Emseal AST? Thanks for your help and hopefully I can order a new building from you in the future. ZACH in BLACK CREEK

DEAR ZACH: Thank you very much for your kind words! I will guess your building has no endwall overhangs, if this is the case the best way to seal up those endwalls is to use Emseal AST (https://www.hansenpolebuildings.com/2016/03/emseal-self-expanding-sealant-tape-closures/) between the rake trims and the endwall steel.

 

If you have endwall overhangs, you should be able to use spray foam in a can (such as Great Stuff or Tite Foam) from inside of the building to spray up the high ribs of the endwall steel.