Clip-Lock Standing Seam, Adding a Ceiling, and Knee Brace Issues

This week Mike the Pole Barn Guru answers reader questions about replacing roofing with clip-lock standing seam and what the PBG recommends in the scenario, creating a wood shop in an existing structure and wondering if ceiling weight can be held, the possibility of removing knee braces in order to install a ceiling.

DEAR POLE BARN GURU: I am leaning toward replacing with clip lock standing seam on 2×4 purlins every foot on center. My installer wants to do away with the vapor barrier and stretch synthetic underlayment over the purlins. What do you recommend in this scenario? JAVO in PRINCE FREDERICK

DEAR JAVO: Clip lock standing seam panels have no ability to transfer wind shear loads and should only be installed over 5/8″ CDX plywood sheathing. If not, your building is likely to rack (or even fail) due to wind loads. There are other reasons to use sheathing: https://www.hansenpolebuildings.com/2015/08/standing-seam-steel/ In summary remove vapor barrier, install plywood with synthetic underlayment between plywood and standing seam steel.

 

DEAR POLE BARN GURU: Hello, I have an existing pole barn/garage but I have very little information about it. I would like to create an interior room for a woodshop but I don’t know if my trusses would support a ceiling and the necessary insulation. Is this something you can help with? CHAD in GRASS LAKE

Installing a ceilingDEAR CHAD: Unlike all Hansen Pole Buildings with spans of 40 foot or less (where we have our interior double trusses always designed to be able to support at least a minimal ceiling load of five pounds per square foot), most pole barn trusses are not ordered or designed to support any sort of a ceiling. Many times trusses will have a stamp on them stating truss spacing and loads, if so, you want a Bottom Chord Dead Load of 5 psf or greater. If nothing else, truss manufacturer’s stamp will tell you who fabricated those trusses and you can reach out to them to verify adequacy. If they do not have records available, or are no longer in business, you should engage a Registered Professional Engineer to perform a field inspection to verify adequacy, or to provide an engineered repair.

 

DEAR POLE BARN GURU: I have a 30′ x 48′ x12′ pole barn that has Knee braces. I am wondering if I am able to remove the knee braces on this type of rafter to eliminate having to cut around each one as I am installing interior liner steel. The rafter top chord is 2×10, the bottom chord and webs are 2×6 and the rafters are adjoined to the poles appx 30′ below the bottom chord. The rafters have fink style webs. JOSH in CANBY

DEAR JOSH: In fairly recently built pole barns, I would have encouraged you to reach out to whomever originally engineered your building. Your building obviously has been around (somehow) for more than a few years. I say this “somehow” in all seriousness as your roof system does look questionable. It very well could be compromised by any changes – even weight of steel liner panels. Best bet is this – hire an engineer to do an actual physical examination of your building to determine if knee braces can be removed, any structural changes needed if they are to be removed, as well as adequacy to support any sort of ceiling. Think of this as an investment, rather than an expense, especially if it prevents a failure.

Termite Barriers and Wind Speed, Hidden Fasteners, and Truss Modifications

This week the Pole Barn Guru tackles reader questions about termites that can destroy treated lumber in an area wind 80mph winds, if one can install a roof with hidden fasteners over trusses or if it needs an underlayment, and the possibility of modifying a truss chord in order to accommodate a overhead door operator.

DEAR POLE BARN GURU: We have terrible subterranean termites that can destroy treated lumber. We also live in an area that sees 80 mph winds in the winter. Are your pole barns strong enough to withstand these things? DAN in FRAZIER PARK

DEAR DAN: Every Hansen Pole Building is fully engineered to meet or exceed your jurisdiction’s minimum design wind speed requirements (in Ventura county Vult = 100 mph). When wind is a client concern, we always recommend designing to higher than minimum design wind speeds. In many instances, added investments are minimal. Most important is designing to correct wind exposure for your particular site. Most other providers sell Exposure B rated buildings, when many sites are actually Exposure C. For extended reading on wind exposure, please read: https://www.hansenpolebuildings.com/2022/06/wind-exposure-and-confusion-part-iii/ While our buildings come with any pressure preservative treated wood at or above Building Code requirements. Regardless of structural building system in areas prone to subterranean termites treat prepared soil with a termiticide barrier at a rate of one gallon of chemical solution per every 10 square feet.

 

DEAR POLE BARN GURU: I want hidden fastener steel roof, do I need to sheath the roof or can I install over trusses. Also, how far apart are your trusses for residential pole barn homes? JAY in MILWAUKEE

DEAR JAY: Hidden fastener steel should only be installed over solid sheathing as it has no shear value to be able to transfer wind loads from roof to endwalls. https://www.hansenpolebuildings.com/2015/08/standing-seam-steel/

In most instances, our fully engineered post-frame barndominiums are designed with a pair of trusses directly aligned with columns every 12 feet.

 

DEAR POLE BARN GURU: Would it be possible to install a 1/8- 1/4 ‘’ steel plate C-shaped with a “tail” extending from back side to tie a bottom chord and king post together and then cut out a 6’’ section to allow for a garage door opener install. GABE in SIMCOE

DEAR GABE: Maybe, however no truss should ever be cut or modified unless done with an engineer certified repair. https://www.hansenpolebuildings.com/2016/07/cutting-trusses/

 

 

Financing a Shouse, Drawings, and Roofing advice

This week the Pole Barn Guru answers questions about financing a Shouse, a timeline for plans to build a large pole barn, advice for roofing with standing seam steel.

DEAR POLE BARN GURU: We are in the process of selling our home and buying a piece of property to build on. We want to build a pole barn home that is 40×80, half shop, half 2 story home (shouse).

Because we don’t own the property yet, what is the best way to go about financing this project?? Where do you start? How do you find out what types of financing are available? Any advice would be appreciated. HEATHER in DEER PARK

DEAR HEATHER: Reach out to New Century Bank as they specialize in post frame financing nationwide https://www.newcenturybankna.com/lending/post-frame-building-leases-loans

Here are some plan tips – consider these factors:

Direction of access (you don’t want to have to drive around your house to get to garage doors)

‘Curb appeal’ – what will people see as they drive up?

Any views?

North-south alignment – place no or few windows on north wall, lots on south wall
Overhang on south wall to shade windows from mid-day summer sun If your AC bill is far greater than your heating bill, reverse this and omit or minimize north overhangs.

Slope of site

Work from inside out – do not try to fit what you need within a pre-ordained box just because someone said using a “standard” size might be cheaper. Differences in dimensions from “standard” are pennies per square foot, not dollars.

Use the links in this article to assist with determining needed spaces, sizes and how to get expertly crafted floor plans and elevation drawings https://www.hansenpolebuildings.com/2019/10/show-me-your-barndominium-plans-please/

 

DEAR POLE BARN GURU: How do I get drawings quickly for a large pole barn, post frame? JAMES in LITTLE SILVER

DEAR JAMES: Your quickest way will be to call 1(866)200-9657 and speak with a Hansen Pole Buildings’ Designer. As soon as you have settled on a building design and get your building order placed, we can get it into our Drafting Department. Depending upon complexity, backlog of work and how quickly you electronically approve documents, you may be able to have your engineer sealed plans and verifying calculations in hand in seven to 10 days.

 

DEAR POLE BARN GURU: I am building my first pole barn. I plan to sheet the roof so i can do standing seem metal and spray foam the roof. I desire to have a thermal break on the top chord of the truss. I am considering laying R max before i sheet the roof. I have tried to find a foam tape or something I can just apply to the top edge of the truss, instead of using R Max to cover the entire structure. Any suggestions? I have set the Purlins between the trusses. STEVE in SOMERSET

DEAR STEVE: As standing seam roofing must be installed over minimum 5/8″ CDX plywood and 30# felt (or a synthetic underlayment) you will already have created a thermal break across your trusses as great as what is provided at your purlin locations.