How to Prevent Existing 6×6 Columns From Future Settling and Rotting

How to Prevent Existing 6×6 to Prevent Future Settling and Rotting

Reader BARRY in FREDERICKTOWN writes:

“I recently acquired some property with an existing pole barn “house” on it. It is an unfinished 20’x30′ room with corrugated steel siding, a trussed, steel covered roof and several doors and windows. It was built with a raised floor attached to the 6×6 treated beams set deep into the rocky soil. Before I make any improvements to the inside of the structure to make it livable I am wondering if there is any process I can do now to set the existing 14 6×6 supports on concrete piers or a footing to prevent future settling and rotting. I cannot see any existing concrete surrounding or supporting the vertical 6×6’s. I would hate to invest anything on the inside of a structure that was not set on a good foundation.”

Mike the Pole Barn Guru writes:
If your existing columns are showing no decay signs then they are probably adequately pressure preservative treated. You could excavate around each column, to below frost line. Hole diameter (to provide sufficient bearing surface) should be determined by an engineer, however for sturdy soils and small spans, usually 24 inch diameters will be sufficient.

Drill each column, in both directions using a 5/8” bit, six to 12 inches above column base. Insert a #4 re-bar dowel (#4 is 1/2″ diameter) through each hole.

Galvanized re-bar is recommended. Otherwise, coat rebar penetrating column with an asphalt emulsion, or similar, to isolate re-bar from pressure treated wood.

Seal rebar, into bored holes, at each column edge with silicone caulking.

Before backfilling holes with premix concrete, make sure floor is level. If not, slowly jack floor up to be level with highest point and temporarily brace.

A recent study has shown concrete in contact with pressure preservative treated pine may encourage premature decay by brown-rot fungi. As such, we strongly recommend isolating such columns from concrete starting at splash plank top (roughly 7-1/4″ above grade), to 14 to 18 inches below grade by use of a moisture impervious barrier. Then backfill holes with pre-mix.

If premature post decay is apparent, here are some other options: https://permacolumn.com/pdfs/perma-column-rotted-posts-repair-guide.pdf

Christmas Morning 2017

Christmas Morning 2017

Christmas morning is traditionally when youngsters awaken their parent far too early – too see what surprises Santa has left them overnight.

On occasion there are surprises for adults as well – some of them not always as desired.

Below pictured are beginnings of an 80 foot wide clearspan by 240 foot long riding arena in Bloomingburg, Ohio, taken just prior to Christmas. Pretty impressive.

As owner of two pre-fabricated metal connector plated wood roof truss manufacturing companies for nearly 20 years, I always got a thrill out of big clearspan trusses.

Special care needs to be used in installing large, clearspan trusses.

This is an excerpt from Structure; August 2009, authored by Dr. Frank Woeste, P.E. and Dr. Donald Bender, P.E.. 

MPC is Metal-Plate-Connected; RDP is Registered Design Professional (architect or engineer).

Responsibilities where the Legal Requirements Mandate a Registered Design Professional for Buildings (Section 2.3 of ANSI/TPI 1)

“In preparation for specifying MPC wood trusses, every section of Chapter 2 and ANSI/TPI 1-2007 (NOTE: ANSI/TPI 1-2014 retains the same language) standard should be carefully studied by the RDP. In preparing this article, we assumed that the RDP will view a complete copy of Chapter 2 for a full understanding. Specific sections selected for discussion are cited by paragraph and subparagraph numbers. 

Under Section 2.3.1 Requirements of the Owner, we note three sections that can help prevent truss erection accidents, and in some cases improve in-service truss performance. Over the past two decades, industry safety documents recommended that for truss spans over 60 feet, the Contractor should “See a registered professional engineer” for temporary bracing information. In many cases, Erection Contractors failed to follow the advice, and some accidents and performance problems stemmed from inadequate temporary and permanent bracing. The new ANSI/TPI 1 standard now requires action by the Owner and RDP as given in the following paragraphs: 

2.3.1.6 Long Span Truss Requirements. 

2.3.1.6.1 Restraint/Bracing Design. 

In all cases where a Truss clear span is 60 feet (18m) or greater, the Owner shall contract with any Registered Design Professional for the design of the Temporary Installation Restraint/Bracing and the Permanent Individual Truss Member Restraint and Diagonal Bracing. 

2.3.1.6.2 Special Inspection 

In all cases where a Truss clear span is 60 feet (18m) or greater, the Owner shall contract with any Registered Design Professional to provide special inspections to assure that the Temporary Installation Restraint/Bracing and the Permanent Individual Truss Member Restraint and Diagonal Bracing are installed properly.” 

The importance of these new paragraphs to truss safety and reliability cannot be overstated. When executed by the Owner and RDP, these provisions for long span trusses should be effective in preventing truss erection accidents and ensuring in-service truss performance.“

Our Hansen Pole Buildings’ Construction Manual, includes a copy of BCSI-B10 “Post Frame Truss Installation and Bracing”. B10 includes instructions on how to properly temporarily brace wall column as well as diagonally across tops of roof purlins – to prevent what was found on this building Christmas morning:

This particular building’s RDP had designed its roof system so as 36 feet of roof closest to each endwall was to be sheathed with 7/16” OSB on top of purlins. Had sheathing been installed, before moving forward, as well as following column, truss and roof plane (purlin) bracing guidelines – this wind induced failure would not have spoiled an otherwise happy Christmas morning.

Responsibilities Where the Legal Requirements Mandate

Responsibilities where the Legal Requirements Mandate a Registered Design Professional for Buildings (Section 2.3 of ANSI/TPI 1)

MPC is Metal-Plate-Connected; RDP is Registered Design Professional (architect or engineer).

In preparation for specifying MPC wood trusses, every section of Chapter 2 and ANSI/TPI 1-2007 (NOTE: ANSI/TPI 1-2014 retains same language) standard should be carefully studied by the RDP. In preparing this article, we assumed that the RDP will view a complete copy of Chapter 2 for a full understanding. Specific sections selected for discussion are cited by paragraph and subparagraph numbers.

Under Section 2.3.1 Requirements of the Owner, we note three sections that can help prevent truss erection accidents, and in some cases improve in-service truss performance. Over the past two decades, industry safety documents recommended that for truss spans over 60 feet, the Contractor should “See a registered professional engineer” for temporary bracing information. In many cases, Erection Contractors failed to follow the advice, and some accidents and performance problems stemmed from inadequate temporary and permanent bracing. The new ANSI/TPI 1 standard now requires action by the Owner and RDP as given in the following paragraphs:

2.3.1.6 Long Span Truss Requirements.

2.3.1.6.1 Restraint/Bracing Design.

In all cases where a Truss clear span is 60 feet (18m) or greater, the Owner shall contract with any Registered Design Professional for the design of the Temporary Installation Restraint/Bracing and the Permanent Individual Truss Member Restraint and Diagonal Bracing.

2.3.1.6.2 Special Inspection

In all cases where a Truss clear span is 60 feet (18m) or greater, the Owner shall contract with any Registered Design Professional to provide special inspections to assure that the Temporary Installation Restraint/Bracing and the Permanent Individual Truss Member Restraint and Diagonal Bracing are installed properly.”

The importance of these new paragraphs to truss safety and reliability cannot be overstated. When executed by the Owner and RDP, these provisions for long span trusses should be effective in preventing truss erection accidents and ensuring in-service truss performance. “